- Consultation - August 2009
- Completion of Detailed Design Stage - September 2009
- Submission of Planning Application - September 2009
- Planning Approved - December 2009
- Appointment of Main Contractor , Wates Construction - March 2010
- Start date for Main Contractor - May 2010
- Planned completion of construction Phase May 2012
- Fit out period - May to July 2012
- Staff relocate to new building - July 2012
- Building open for teaching - September 2012
The construction phase is making good progress. The target is for the steelframe erection to be complete in February 2011, and for the building to be wind and water tight by summer.