Capital Projects
To view our current works programme for Byrom Street Campus have a look at the Contractors Site Logistic Plan. This shows all the work we are dealing with in the summer rollout.
Faq Items
Mount Pleasant Campus
Copperas Hill
- The planning application has been submitted for the student life and sports buildings.
- The next stage is the procurement of the contractor.
- Start on site scheduled for Winter 2018.
4-6 Rodney Street - Liverpool Business School (LBS)
- Following the competitive tender exercise, Senate Group were appointed as the contractor for the project.
- Work started on the site on Monday 21 May.
Haigh Building
- Work continues on the adjoining site that will form part of a development to bring forward new student residences and a new academic teaching building for LJMU.
John Lennon Art & Design Building
- X-Gallery – Progressed to stage 4 design development. Works scheduled for late July into October.
- Boiler flue installation – Works will take place over the summer.
- Electrical works installing power poles on 4th floor to replace floor boxes. To be complete September.
Redmonds Building
- Minor refurbishment of office space, room 318 to be conducted over summer.
John Foster
- Works ongoing within basement to upgrade DDA facilities and improve access including automatic doors, hold open devices and works to stairwell.
- Teaching rooms 205-210 and room 204 will be refurbished over the summer. Due to be released for tender. Works to take place July to September.
- Exterior decoration to rear of building (Moot room to Student Union area) over the summer.
- Electrical work – various minor works over the summer period.
- External fire-escape stairs will be replaced.
- Drama studio – Mechanical and Electrical works over the summer.
Aldham, Aquinas and Pavilion
- Stage 3 design is due to be completed early June when the planning application for the Pavilion will be submitted.
- Site investigation will commence shortly in the John Foster garden area. A start on site for the Pavilion is scheduled for Autumn 2018.
- The next stage is contractor procurement.
- The Aldham refurbishment is scheduled to start in late Summer 2019 following completion of the Pavilion with Aquinas commencing Summer 2020 following SLB completion.
City Campus
James Parsons
- Passive fire protection works planned throughout building.
- Phase 1 and 2 - Summer works refurbishment of office space on 2nd, 6th and 7th floors out for tender mid-May.
- Phase 3 - Summer works - Faculty of Science lab, office and teaching space refurbishment 1st and 2nd floor.
Modular houses (Urban Splash and Flood Safe)
- Planning application submitted, works scheduled for summer.
Smart Flower (solar panel system)
Peter Jost
- Refurbishment of 1st and 2nd floor office and lab/teaching spaces for summer works. Out for tender mid-May.
- Passive fire protection works planned throughout building.
- New chiller to be installed during the summer to provide cooling within the building.
Engineering Annex
- Refurbishment of G.02 office space during summer works.
Tom Reilly
- Passive fire protection works planned throughout building.
Waste Compound
- Design agreed, tender process underway, works scheduled over summer period.
Marybone, Peter Jost Upper and Cherie Booth
- Lecture theatre and lobby refurbishment:
- Kier have been appointed to undertake works which will be delivered over summer for start of semester one.
- Works include improved lighting, new seating layout, new AV and redecoration
Avril Robarts Roof
- The tender process for this work has been completed and the contract has been awarded.
Tithebarn Street and Avril Robarts
- The Tithebarn and Avril projects have been combined - due to their proximity and programme requirements.
- Stage 3 design for both projects will be completed by mid-June. Contractor procurement has commenced.
- The initial decant will commence early June with all books from the 1st and 2nd floors at Avril being placed on the 3rd floor - prior to the lift replacement project.
- Staff decant from Tithebarn will commence in early August and the IT suite in the Space will be temporarily relocated to the former admin area on 1st floor.
- Information boards for the project have been placed in Avril reception.
Henry Cotton
- Public Health Institute are relocating from 2nd floor to Exchange Station early July. Following this move Nursing and Allied Health staff offices will decant on temporary basis to Henry Cotton.
- Works to upgrade fire doors in core areas will be completed over the summer.
- Works to replace fire doors to risers and fire escape routes due to begin 29 May.
Exchange Station
- Public Health Institute (PHI) 3rd floor. Work began on site Monday 30 April for 11-week programme.
- Amendments to lease in progress for adaptions to first and second floor areas in order to relocate CBCI and Corporate Comms.
Great Crosshall Street
- Works to staircase 3 – Plastering is now complete and redecoration is in progress. Expected completion date 1 June.
IM Marsh Campus
Holmefield House and Primary Base
- Staircase refurbishment is underway (laying new vinyl floor), due to complete 30 May, carried out by Crown Flooring.
- Various mechanical works underway at IM Marsh campus.